A typical UK domestic driveway takes 1–3 days on site. Here's how the programme fits together.
Survey to install
Survey within 5 working days of enquiry. Written quote within 48 hours. Install slots typically 4–8 weeks out in peak season.
On-site programme
Day 1: prep and base if needed. Day 2: resin install. Day 3: edges and finishing. On overlays, often reduced to a single day.
When can you use it?
Foot traffic after 4–6 hours. Vehicles after 24 hours. Full cure at 72 hours.